07-20-2008, 10:45 PM
|
Senior Member
|
|
Join Date: Sep 2007
Posts: 108
|
|
Bixby vs Rosson
Rosson vs Bixby
Quote:
MARK J. BIXBY, individually and dba MJB/BIXBY CONSTRUCTION,
21 INC. and MJB/BIXBY CONSTRUCTION, INC. failed and refused to complete its
22 performance as required by the CONTRACT. Such work as was performed by MARK J.
23 BIXBY, individually and dba MJB/BIXBY CONSTRUCTION, INC. and MJB/BIXBY
24 CONSTRUCTION, INC. pursuant to the CONTRACT was not performed In a
25 workmanlike manner and in accordance with the standards of the industry.
26 III
27
|
|