This reply is to allow for more uploaded documents from the Doty case
Quote:
7. Mr. Bixby and Bixby lnc. did not complete the work under the contract in a
timely manner or satisfactorily. The work, which was to have taken only three to four
weeks, as represented to us by Mr. Bixby and Bixby Inc., actually extended over a five month
period from May 2001 to October 2001. Despite multiple requests that the work
be completed within the time period represented, Mr. Bixby and Bixby Inc. did not
complete the work within that time
|